Professional EVM dashboard for project managers, PMP® candidates, and cost engineers.Compute PV, EV, AC, CPI, SPI, EAC, ETC, VAC, and TCPI instantly. Visualize performance trends with interactive gauges and charts.
Earned Value Management (EVM) is a project control methodology that integrates scope, schedule, and cost data to provide objective performance measures. Recognised by the Project Management Institute (PMI®) and formalised in the PMBOK® Guide, EVM is the gold standard for forecasting project outcomes and identifying deviations early. This calculator implements the core EVM formulas as defined in the Practice Standard for Earned Value Management (PMI, 2019).
Core EVM Metrics
All metrics follow PMI® EVM standard definitions. CPI and SPI > 1.00 indicate favorable performance; < 1.00 indicates unfavorable.
Planned Value (PV): The authorized budget assigned to scheduled work. It represents the value of work that should have been completed by a given date.
Earned Value (EV): The value of work actually performed, expressed in terms of the approved budget. EV is the most objective measure of progress.
Actual Cost (AC): The total cost incurred for the work performed. AC is derived from actual invoices, timesheets, and expense reports.
Cost Performance Index (CPI): A ratio of EV to AC. CPI = 1.00 means on budget; > 1.00 means under budget; < 1.00 means over budget. CPI is the most reliable indicator of cost efficiency.
Schedule Performance Index (SPI): A ratio of EV to PV. SPI = 1.00 means on schedule; > 1.00 means ahead of schedule; < 1.00 means behind schedule.
Estimate at Completion (EAC): The projected total cost of the project at completion. The formula EAC = BAC / CPI is used when CPI is expected to remain stable. Other EAC formulas exist (e.g., EAC = AC + (BAC – EV) / (CPI × SPI)), but this calculator uses the standard PMI formula.
Estimate to Complete (ETC): The expected cost to finish all remaining work. ETC = EAC – AC.
Variance at Completion (VAC): The difference between BAC and EAC. A negative VAC indicates a projected cost overrun.
To‑Complete Performance Index (TCPI): The required cost performance efficiency (CPI) that must be achieved on the remaining work to meet the BAC. TCPI = (BAC – EV) / (BAC – AC). A TCPI > 1.00 means the remaining work must be performed more efficiently than planned.
Bridge Construction – Western Australia (2023–2025)
A major bridge project with a BAC of $120M was 40% complete when EVM revealed CPI = 0.72 and SPI = 0.68. The project was both over budget and behind schedule. Using the PMI Calculator, the project control team computed:
The team implemented a recovery plan: accelerated procurement, renegotiated subcontractor rates, and added a second shift. After 6 months, CPI improved to 0.89 and SPI to 0.92. The final EAC was revised to $138M, saving $28.7M from the worst‑case forecast. This case demonstrates how EVM metrics guide data‑driven decisions and turnaround strategies.